2012-07-30 - 4629.100 - Spec - Improve manual monthly COPA adjust. proc #PCASub

SPECIFICATIONS

4629.100 - Improve manual monthly COPA adjust. proc

Purpose


Assign appropriate factory calendars to routes.

Admin Info


Purpose
Improve manual monthly COPA adjust. proc
Requested By

Spec Created By
Sai Valisetti
Spec Created Date
11/27/2012
Spec QA by
Jingsha
Objects

Document Status
WIP

References


Prior Tickets

5339-100-No longer able to print packslips for STO deliveries (9-15-12)

Documents

Routes-Test.xlsx


Functional Requirement


The delivery dates in the sales documents are pushed into the future though inventory available. The wrong factory calendars are assigned in the routes that is pushing the dates into the future



Solution Summary


[Discuss this section with Requester and get approval prior to beginning work]
The solution involves correcting the appropriate calendar to the routes as specified in the file “Update Routes.xlsx”. In order that the new delivery dates kick in for the affected sales orders, ATP should be re-run or rescheduling should be done for the orders with the combination of the materials and plants.


Test Plan

[List test scenarios/cases to be executed here]

Test Scenario
Expected Results
1
Create SOwith sales org 1000, plant 7410 and route DRMMAR
The delivery dates should be calculated based on calendar Z8
2
Create SOwith sales org 2000, plant 0510 and route HKWEAR
The delivery dates shoud be calculated based on calendar Z7

Solution Details


[Provide complete technical details for configuration or programming here]